Part of the Understand how to apply and tailor relevant aspects of the MSP processes in context domain, which makes up ~55% of our current practice bank. PeopleCert does not publish an official question count, but from its 150-minute exam (~60–100 total, ~33–55 in this domain), expect 2–4 from this objective — we provide 27 practice questions to prepare you well beyond it. (estimate)
27questions here
6free pages
5concepts
Questions 6–10
- 6
Which role is responsible for developing the tranche delivery plans in the 'plan progressive delivery' process?
Select an answer first - 7
A telecommunications programme is planning the progressive delivery of a new billing system. The programme manager has defined the tranches and is now working with the tranche teams to refine the details of the first tranche. Which activity is the programme manager performing?
Select an answer first - 8
A financial services programme is planning the progressive delivery of a new customer onboarding system. The programme board has approved the tranche structure, but the tranche teams are unclear about their specific responsibilities for delivering the first tranche. Who should clarify the tranche team's responsibilities and ensure they understand the tranche's scope and objectives?
Select an answer first - 9
A healthcare programme is planning the progressive delivery of a new patient records system. The programme manager is defining the tranches and needs to ensure that each tranche delivers a coherent set of capabilities that can be operated independently. Which MSP theme should the programme manager apply most directly to this activity?
Select an answer first - 10
A retail banking programme is planning the progressive delivery of a new mobile app. The programme manager has defined the tranches and is now working with the tranche teams to identify the specific projects that will deliver the tranche's capabilities. Which activity is the programme manager performing?
Select an answer first