3.3.1 Carry Out the ‘plan Progressive Delivery’ Process MSP-PRACTITIONER-5TH-EDITION Practice Questions (Page 1)

Part of the Understand how to apply and tailor relevant aspects of the MSP processes in context domain, which makes up ~55% of our current practice bank. PeopleCert does not publish an official question count, but from its 150-minute exam (~60–100 total, ~33–55 in this domain), expect 2–4 from this objective — we provide 27 practice questions to prepare you well beyond it. (estimate)

27questions here
6free pages
5concepts

Questions 1–5

  1. 1expert · hard

    A financial services programme is planning the progressive delivery of a new customer onboarding system. The programme manager has defined the tranches, but the tranche teams are unclear about their specific responsibilities for delivering the first tranche. The programme manager is also concerned that the business change manager is not sufficiently involved in the tranche planning. What should the programme manager do?

    Select an answer first
  2. 2foundation · easy

    Which output of the 'plan progressive delivery' process details the specific activities, resources, and dependencies for each tranche?

    Select an answer first
  3. 3expert · hard

    A pharmaceutical programme is completing the 'plan progressive delivery' process. The programme manager has produced the tranche descriptions and the updated programme plan. However, the programme board is concerned that the governance arrangements for the tranches are not clear. What should the programme manager do?

    Select an answer first
  4. 4application · medium

    A utilities programme is planning the progressive delivery of a new customer service platform. The programme board has approved the tranche structure, and the programme manager is now working with the business change manager to ensure that the tranches deliver the expected benefits. Which responsibility is the business change manager performing in this context?

    Select an answer first
  5. 5foundation · easy

    Which activity in the 'plan progressive delivery' process involves defining how the tranches will be governed and how progress will be monitored?

    Select an answer first