3.3.2 Analyse Whether the ‘plan Progressive Delivery’ Process Activities, Roles and Responsibilities Are Effective and Fit for Purpose MSP-PRACTITIONER-5TH-EDITION Practice Questions (Page 1)
Part of the Understand how to apply and tailor relevant aspects of the MSP processes in context domain, which makes up ~55% of our current practice bank. PeopleCert does not publish an official question count, but from its 150-minute exam (~60–100 total, ~33–55 in this domain), expect 2–4 from this objective — we provide 21 practice questions to prepare you well beyond it. (estimate)
21questions here
5free pages
4concepts
Questions 1–5
- 1
Which factor should be considered when tailoring progressive delivery planning for a programme?
Select an answer first - 2
In a programme transitioning to a new operating model, the business change manager has been assigned the role of defining the tranche contents, while the senior supplier is responsible for estimating the effort. The business change manager is new to the organization and lacks detailed knowledge of the operational processes. The tranche definitions are being challenged by the operational teams as unrealistic. What is the most likely cause of this ineffectiveness?
Select an answer first - 3
A programme is delivering a new financial system with a high degree of uncertainty in the requirements. The tranche planning is being done in a very structured way, with detailed tranche definitions and firm dates. The programme manager wants to tailor the process to handle the uncertainty. What is the most appropriate tailoring?
Select an answer first - 4
In a programme, the senior responsible owner (SRO) has been asked to approve the tranche plan. The SRO is also the chief executive and has limited time. The programme manager has prepared a detailed tranche plan with extensive technical detail. The SRO is struggling to understand the business implications and is delaying approval. What should the programme manager do to improve the effectiveness of the approval process?
Select an answer first - 5
A programme is delivering a new IT system with a mix of mandatory regulatory changes and desirable enhancements. The tranche planning is being done with a fixed sequence, and the regulatory changes are scheduled in the last tranche. The programme board is concerned that this creates a risk of non-compliance if the last tranche is delayed. The programme manager wants to adjust the tranche plan to reduce this risk. What is the best approach?
Select an answer first
Finished these 5 questions?
Review the revealed explanations, or continue through the curriculum.