Part of the Project management concepts domain, which accounts for 33% of the PK0-005 exam. CompTIA does not publish an official question count, but from its 90-minute exam (~35–60 total, ~12–20 in this domain), expect 1–2 from this objective — we provide 36 practice questions to prepare you well beyond it. (estimate)

36questions here
8free pages
10concepts
33%of the exam

Questions 36–36

  1. 36application · medium

    A project manager is leading a project to upgrade a company's network infrastructure. A proposed change would replace a network switch model with a different vendor's product. The project manager has completed the impact analysis and presented it to the Change Control Board. The CCB is composed of the project sponsor, the IT director, and a network engineer. What is the CCB's role in this situation?

    Select an answer first
Finished these 1 questions?

Review the revealed explanations, or continue through the curriculum.

No more pagesBack to PK0-005

Free Basic Practice is a study aid with revealable answers — not a scored exam. Examers.io is independent and not affiliated with or endorsed by CompTIA. “PK0-005” is a trademark of its owner, used for identification only.