Task 3 Provide Information Required to Update Relevant Project Documents PMI-RMP Practice Questions (Page 5)

Part of the Monitor and Close Risks domain, which accounts for 19% of the PMI-RMP exam. PMI does not publish an official question count, but from its 230-minute exam (~90–155 total, ~17–29 in this domain), expect 4–7 from this objective — we provide 24 practice questions to prepare you well beyond it. (estimate)

24questions here
5free pages
4concepts
19%of the exam

Questions 21–24

  1. 21foundation · easy

    Which step is part of closing out an expired risk?

    Select an answer first
  2. 22foundation · easy

    Which project document is most commonly updated with aggregated risk data during monitoring?

    Select an answer first
  3. 23foundation · easy

    What is the primary purpose of formally closing an expired risk?

    Select an answer first
  4. 24expert · hard

    A project manager is preparing a risk summary for a steering committee. The summary must show the current risk exposure, but the risk register contains several risks that have passed their trigger dates without occurring. The project manager has not yet reviewed these expired risks. What should the project manager do?

    Select an answer first
Finished these 4 questions?

Review the revealed explanations, or continue through the curriculum.

No more pagesBack to PMI-RMP

Free Basic Practice is a study aid with revealable answers — not a scored exam. Examers.io is independent and not affiliated with or endorsed by PMI. “PMI-RMP” is a trademark of its owner, used for identification only.