Task 4 Monitor Project Risk Levels PMI-RMP Practice Questions (Page 1)

Part of the Monitor and Close Risks domain, which accounts for 19% of the PMI-RMP exam. PMI does not publish an official question count, but from its 230-minute exam (~90–155 total, ~17–29 in this domain), expect 4–7 from this objective — we provide 19 practice questions to prepare you well beyond it. (estimate)

19questions here
4free pages
3concepts
19%of the exam

Questions 1–5

  1. 1application · medium

    A project manager is communicating the current risk level to stakeholders. The overall risk score is 22, which is above the threshold of 20. The project manager wants to ensure stakeholders understand the urgency and the need for action. Which communication approach is most effective?

    Select an answer first
  2. 2application · medium

    A project manager must report risk levels to the project sponsor, who prefers visual summaries, and to the risk management team, who need detailed data. The sponsor has limited time and wants to see the top five risks and overall trend. The risk team needs to review all risks and their response status. Which reporting strategy is most effective?

    Select an answer first
  3. 3foundation · easy

    When communicating current project risk levels to key stakeholders, what is the most important factor to ensure the communication is effective?

    Select an answer first
  4. 4application · medium

    A project manager is aggregating individual risk assessments to determine the overall project risk level. The project has a risk threshold of 20 on a 0–100 scale. The individual risk scores are: Risk 1 = 15, Risk 2 = 10, Risk 3 = 5. The project manager uses a weighted scoring model where Risk 1 has a weight of 0.5, Risk 2 has a weight of 0.3, and Risk 3 has a weight of 0.2. What is the overall project risk score and the resulting risk level?

    Select an answer first
  5. 5application · medium

    A project manager discovers that a critical risk has increased in probability from 0.3 to 0.7, pushing the overall project risk level above the threshold. The next stakeholder meeting is in two weeks. What is the most appropriate action regarding communication?

    Select an answer first