PMIRisk Management Professional
Domain 5Objective 1
Task 1 Gather and Analyze Performance Data PMI-RMP Practice Questions (Page 1)
Part of the Monitor and Close Risks domain, which accounts for 19% of the PMI-RMP exam. PMI does not publish an official question count, but from its 230-minute exam (~90–155 total, ~17–29 in this domain), expect 4–7 from this objective — we provide 19 practice questions to prepare you well beyond it. (estimate)
19questions here
4free pages
4concepts
19%of the exam
Questions 1–5
- 1
A construction project has multiple work packages. The risk register identifies a high-risk foundation package. The project manager receives weekly status reports from all package leads. During reconciliation, the PM notices that the foundation package's reported percent complete is 80%, but the earned value data from the cost system shows only 65% of the budget consumed. The PM suspects the package lead is reporting progress optimistically. What should the PM do first?
Select an answer first - 2
A project is experiencing significant schedule delays in a critical work package. The project manager has calculated a schedule variance of -$30,000 and a schedule performance index (SPI) of 0.8. The project manager needs to communicate the impact on overall project risk exposure to enterprise stakeholders. What is the most important information to include?
Select an answer first - 3
A project manager is monitoring the impact of performance variances on overall project risk exposure. The project has a cost performance index (CPI) of 0.9 and a schedule performance index (SPI) of 0.85. The project sponsor asks for a summary of the risk exposure. Which statement is most accurate?
Select an answer first - 4
A project manager is consolidating performance data from multiple work packages to update the risk register. The PM notices that one work package's reported progress is inconsistent with its actual deliverables. The package lead explains that the progress was reported based on the percentage of budget spent, not on completed deliverables. What should the PM do?
Select an answer first - 5
A project manager is performing variance analysis for a work package. The schedule variance (SV) is -$8,000, and the cost variance (CV) is -$3,000. The PM has identified that the schedule delay is due to a key resource being unavailable, and the cost overrun is due to overtime pay. The PM needs to determine the impact on project risk. Which action is most appropriate?
Select an answer first
Finished these 5 questions?
Review the revealed explanations, or continue through the curriculum.