Part of the Monitor and Close Risks domain, which accounts for 19% of the PMI-RMP exam. PMI does not publish an official question count, but from its 230-minute exam (~90–155 total, ~17–29 in this domain), expect 4–7 from this objective — we provide 26 practice questions to prepare you well beyond it. (estimate)

26questions here
6free pages
7concepts
19%of the exam

Questions 1–5

  1. 1foundation · easy

    Why is it important to communicate the impact of residual and secondary risks to stakeholders?

    Select an answer first
  2. 2foundation · easy

    What is the most effective way to communicate risk impacts to stakeholders?

    Select an answer first
  3. 3expert · hard

    A project manager is reviewing the risk register and finds that a secondary risk was identified but has not been assigned an owner or a response. The secondary risk is now materializing. What should the project manager do?

    Select an answer first
  4. 4foundation · easy

    When assessing the impact of residual and secondary risks, which project objectives should be considered?

    Select an answer first
  5. 5expert · hard

    A project manager is monitoring a risk response that was designed to reduce the probability of a supplier failure by dual-sourcing a critical component. The primary supplier has been performing well, and the secondary supplier has not been used. The risk owner suggests closing the risk because the response is working. What should the project manager do?

    Select an answer first