Task 2 Monitor Residual & Secondary Risks PMI-RMP Practice Questions (Page 3)

Part of the Monitor and Close Risks domain, which accounts for 19% of the PMI-RMP exam. PMI does not publish an official question count, but from its 230-minute exam (~90–155 total, ~17–29 in this domain), expect 4–7 from this objective — we provide 26 practice questions to prepare you well beyond it. (estimate)

26questions here
6free pages
7concepts
19%of the exam

Questions 11–15

  1. 11application · medium

    A project team implemented a contingency plan to outsource a critical component after a supplier delay. This created a secondary risk of quality issues with the new supplier. The project manager has been tracking this secondary risk for three weeks. The quality issues have not materialized, and the new supplier's performance is exceeding expectations. What should the project manager do?

    Select an answer first
  2. 12application · medium

    A project team implemented a risk response to reduce the risk of a key team member leaving by cross-training another team member. During the next risk review, the project manager discovers that the cross-training is not progressing as planned and the backup team member is not yet competent. What should the project manager do?

    Select an answer first
  3. 13application · medium

    A project implemented a risk response that reduced the probability of a major cost overrun. However, a significant residual risk remains. The project manager needs to communicate this to the project sponsor. What is the MOST effective way to communicate the residual risk?

    Select an answer first
  4. 14foundation · easy

    A residual risk has a high probability of causing a delay in the project schedule. Which project objective is directly affected?

    Select an answer first
  5. 15expert · hard

    A project implemented a risk response to reduce the risk of a cyberattack by adding a new firewall. This created a secondary risk of network performance degradation. The project manager is deciding how to manage this secondary risk. The network performance is critical for the project's daily operations. What is the BEST approach?

    Select an answer first