Task 2 Monitor Residual & Secondary Risks PMI-RMP Practice Questions (Page 5)
Part of the Monitor and Close Risks domain, which accounts for 19% of the PMI-RMP exam. PMI does not publish an official question count, but from its 230-minute exam (~90–155 total, ~17–29 in this domain), expect 4–7 from this objective — we provide 26 practice questions to prepare you well beyond it. (estimate)
26questions here
6free pages
7concepts
19%of the exam
Questions 21–25
- 21
A project implemented a risk response to reduce the risk of a cost overrun by using a cheaper material. This created a secondary risk of quality issues. The quality issues have materialized, causing rework and a potential delay. The project has a tight budget and a fixed deadline. What is the MOST critical impact to assess?
Select an answer first - 22
A project team implements a risk response that introduces a new risk. How is this new risk classified?
Select an answer first - 23
What is the purpose of tracking the execution of planned risk responses?
Select an answer first - 24
When should the risk register be updated with residual and secondary risk information?
Select an answer first - 25
After implementing a risk response, what does 'residual risk' represent?
Select an answer first