Task 1 Perform Qualitative Analysis PMI-RMP Practice Questions (Page 1)
Part of the Risk Analysis domain, which accounts for 23% of the PMI-RMP exam. PMI does not publish an official question count, but from its 230-minute exam (~90–155 total, ~21–36 in this domain), expect 7–12 from this objective — we provide 27 practice questions to prepare you well beyond it. (estimate)
27questions here
6free pages
6concepts
23%of the exam
Questions 1–5
- 1
In qualitative risk analysis, the team is estimating the impact of a risk on the project's schedule. Which scale would be most appropriate for this assessment?
Select an answer first - 2
A project uses a 5x5 probability-impact matrix. The risk management plan defines that risks with a score of 15 or higher are 'Critical' and require immediate response planning. A risk has a probability of 5 (Almost Certain) and an impact of 3 (Moderate). What is the risk score and the required action?
Select an answer first - 3
When using an ordinal scale to classify risks, which of the following is a valid example?
Select an answer first - 4
Which statement best describes ordinal classification of risks?
Select an answer first - 5
A project has two risks: Risk A is a technical risk with a score of 12 (High) and is expected to occur in 3 months. Risk B is an organizational risk with a score of 9 (Medium) but is expected to occur within 1 month. The project has limited resources to address only one risk this week. What should the risk manager recommend?
Select an answer first