Task 1 Perform a Preliminary Document Analysis PMI-RMP Practice Questions (Page 1)
Part of the Risk Strategy and Planning domain, which accounts for 22% of the PMI-RMP exam. PMI does not publish an official question count, but from its 230-minute exam (~90–155 total, ~20–34 in this domain), expect 3–6 from this objective — we provide 22 practice questions to prepare you well beyond it. (estimate)
22questions here
5free pages
3concepts
22%of the exam
Questions 1–5
- 1
A project manager is starting the preliminary document analysis for a project that involves multiple vendors. The risk manager has identified that the vendor contracts are critical for understanding potential risks. However, the contracts are stored in a legal repository that requires special permissions. What is the most effective way to ensure these documents are available for the analysis?
Select an answer first - 2
A risk manager is leading the preliminary document analysis for a project that is a merger of two companies' IT systems. The project has a very aggressive timeline, and the project manager is new to the organization. The risk manager has access to the project charter, the business case, and the stakeholder register. The risk manager also needs to review the technical architecture documents, but they are incomplete and still being developed. What is the most effective approach?
Select an answer first - 3
In the preliminary document analysis, which role is typically responsible for determining which documents are relevant to the risk process and ensuring they are available?
Select an answer first - 4
Why is it important to ensure that risk-relevant documents are accessible to the team performing the preliminary document analysis?
Select an answer first - 5
A project manager is starting risk planning for a large infrastructure project. The sponsor has provided the project charter, the business case, and the stakeholder register. The project manager wants to ensure the risk management plan is based on a thorough understanding of the project. Which additional document should the project manager prioritize for review to identify potential risks related to scope and schedule?
Select an answer first