Task 1 Perform a Preliminary Document Analysis PMI-RMP Practice Questions (Page 2)

Part of the Risk Strategy and Planning domain, which accounts for 22% of the PMI-RMP exam. PMI does not publish an official question count, but from its 230-minute exam (~90–155 total, ~20–34 in this domain), expect 3–6 from this objective — we provide 22 practice questions to prepare you well beyond it. (estimate)

22questions here
5free pages
3concepts
22%of the exam

Questions 6–10

  1. 6foundation · easy

    Which of the following is an example of a project document that would typically be collected and reviewed during the preliminary document analysis for risk management?

    Select an answer first
  2. 7foundation · easy

    During the preliminary document analysis for a new project, the risk manager needs to identify and collect all relevant project documents. Which of the following is the PRIMARY purpose of this step?

    Select an answer first
  3. 8expert · medium

    A risk manager is leading the preliminary document analysis for a project that is a major organizational change. The project has a high level of stakeholder interest, and the risk manager has identified that the change management plan is critical for understanding risks. However, the change management plan is owned by a different department and is not readily accessible. What is the most effective way to obtain this document?

    Select an answer first
  4. 9application · medium

    A risk manager is starting the preliminary document analysis for a project that is a follow-on to a previous project. The previous project's lessons learned and risk register are available. The risk manager wants to use these to inform the current analysis. What is the most important consideration when using these historical documents?

    Select an answer first
  5. 10application · easy

    A risk manager is conducting a preliminary document analysis for a project that has a high level of regulatory oversight. The project manager has provided the project charter, the business case, and the stakeholder register. The risk manager needs to identify risks related to compliance. Which document should the risk manager request to review?

    Select an answer first