Task 1 Perform a Preliminary Document Analysis PMI-RMP Practice Questions (Page 3)

Part of the Risk Strategy and Planning domain, which accounts for 22% of the PMI-RMP exam. PMI does not publish an official question count, but from its 230-minute exam (~90–155 total, ~20–34 in this domain), expect 3–6 from this objective — we provide 22 practice questions to prepare you well beyond it. (estimate)

22questions here
5free pages
3concepts
22%of the exam

Questions 11–15

  1. 11expert · hard

    A risk manager is planning the preliminary document analysis for a project that is a joint venture between a public agency and a private company. The project has a complex governance structure, and the risk manager has identified that the partnership agreement is critical. The agreement is available, but it is lengthy and complex. The risk manager has limited time and needs to identify the key risks. Which approach is most effective?

    Select an answer first
  2. 12application · easy

    A risk manager is conducting a preliminary document analysis for a project that involves a new technology. The project charter and the business case are available, but the risk manager is concerned about the lack of technical documentation. Which document would be most important to request to understand the technical risks?

    Select an answer first
  3. 13application · medium

    A risk manager is leading the preliminary document analysis for a project with a very detailed and technical scope. The project manager is available, but the risk manager is concerned that the project manager may not have the deep technical expertise needed to identify all technical risks. Which approach would be most effective for assigning the document analysis?

    Select an answer first
  4. 14application · easy

    A risk manager is preparing for a preliminary document analysis for a new product launch. The project manager has provided the project charter, the business case, and the stakeholder register. The risk manager also needs to review the project schedule and budget. Who is typically responsible for ensuring these additional documents are available and accessible for the analysis?

    Select an answer first
  5. 15foundation · easy

    When assigning responsibility for conducting the preliminary document analysis, which of the following is a key consideration?

    Select an answer first
Finished these 5 questions?

Review the revealed explanations, or continue through the curriculum.