Part of the Risk Analysis domain, which accounts for 23% of the PMI-RMP exam. PMI does not publish an official question count, but from its 230-minute exam (~90–155 total, ~21–36 in this domain), expect 7–12 from this objective — we provide 27 practice questions to prepare you well beyond it. (estimate)
27questions here
6free pages
6concepts
23%of the exam
Questions 16–20
- 16
A risk manager is coaching stakeholders on risk categorization. What is the primary benefit of using a consistent categorization strategy?
Select an answer first - 17
A project team is prioritizing risks. Which combination of impact and urgency would indicate that a risk requires the most immediate attention?
Select an answer first - 18
A project has a risk with a score of 15 (High) that is not expected to occur for another 6 months. Another risk has a score of 8 (Medium) but could occur within the next 2 weeks. The project sponsor asks which risk should be addressed first. What should the risk manager recommend?
Select an answer first - 19
In a probability-impact matrix, a risk with a probability of 0.8 and an impact of 0.5 would receive a risk score of:
Select an answer first - 20
During qualitative risk analysis, the team is prioritizing risks. Which factor, in addition to impact, is used to determine which risks require immediate attention?
Select an answer first