Part of the Monitor and Close Risks domain, which accounts for 19% of the PMI-RMP exam. PMI does not publish an official question count, but from its 230-minute exam (~90–155 total, ~17–29 in this domain), expect 4–7 from this objective — we provide 19 practice questions to prepare you well beyond it. (estimate)
19questions here
4free pages
4concepts
19%of the exam
Questions 11–15
- 11
A project manager is performing variance analysis for a work package. The planned cost for the completed portion of work is $20,000, but the actual cost incurred is $25,000. The project manager needs to identify the root cause of this cost variance. Which action is most appropriate?
Select an answer first - 12
A project manager is consolidating performance data from multiple work packages. One work package is reporting a schedule variance of -$12,000, but the PM discovers that the package lead has been reporting progress based on the percentage of time elapsed, not on completed deliverables. The PM also finds that the cost data includes a one-time charge that was incorrectly allocated to this package. What is the most appropriate action?
Select an answer first - 13
How do variances in project performance affect overall project risk exposure?
Select an answer first - 14
A risk manager is preparing for a risk review meeting. Which source would be most appropriate to include when reconciling performance data from risk-relevant work packages?
Select an answer first - 15
Which statement best describes the purpose of analyzing completion status against the baseline?
Select an answer first