Part of the Monitor and Close Risks domain, which accounts for 19% of the PMI-RMP exam. PMI does not publish an official question count, but from its 230-minute exam (~90–155 total, ~17–29 in this domain), expect 4–7 from this objective — we provide 19 practice questions to prepare you well beyond it. (estimate)
19questions here
4free pages
3concepts
19%of the exam
Questions 16–19
- 16
A project manager must report risk levels to the project board, which includes members from finance, operations, and IT. The board members have different levels of risk expertise and prefer concise summaries. Which reporting format is most appropriate for this audience?
Select an answer first - 17
A software development project has a risk threshold of 15 on a 1–25 scale. The project manager aggregates individual risk scores: Risk A (probability 4, impact 3), Risk B (probability 5, impact 4), and Risk C (probability 2, impact 5). Using a simple additive scoring model, what is the overall project risk score and the resulting risk level?
Select an answer first - 18
Which of the following best describes the purpose of creating tailored risk reports for different stakeholders?
Select an answer first - 19
During a project status review, the risk manager aggregates the individual risk assessments and compares the total risk exposure to the project's risk thresholds. What is the primary purpose of this activity?
Select an answer first
Finished these 4 questions?
Review the revealed explanations, or continue through the curriculum.
No more pagesBack to PMI-RMP
Free Basic Practice is a study aid with revealable answers — not a scored exam. Examers.io is independent and not affiliated with or endorsed by PMI. “PMI-RMP” is a trademark of its owner, used for identification only.