Part of the Risk Response domain, which accounts for 13% of the PMI-RMP exam. PMI does not publish an official question count, but from its 230-minute exam (~90–155 total, ~12–20 in this domain), expect 6–10 from this objective — we provide 28 practice questions to prepare you well beyond it. (estimate)
28questions here
6free pages
6concepts
13%of the exam
Questions 26–28
- 26
A project manager wants to encourage stakeholders to provide feedback on a recently executed risk response. Which approach is most aligned with this objective?
Select an answer first - 27
After implementing a risk response, the residual risk is assessed to be above the organization's acceptable threshold. What is the most appropriate action?
Select an answer first - 28
A project manager implemented a risk response to reduce the likelihood of a cyberattack by installing a new firewall. After implementation, the project manager assesses the residual risk and finds that the likelihood of a cyberattack is now 10% (down from 40%), but the project's acceptable threshold is 5%. What should the project manager do?
Select an answer first
Finished these 3 questions?
Review the revealed explanations, or continue through the curriculum.
No more pagesBack to PMI-RMP
Free Basic Practice is a study aid with revealable answers — not a scored exam. Examers.io is independent and not affiliated with or endorsed by PMI. “PMI-RMP” is a trademark of its owner, used for identification only.