PMIRisk Management Professional
Domain 4Objective 2
Task 2 Implement Risk Response PMI-RMP Practice Questions (Page 5)
Part of the Risk Response domain, which accounts for 13% of the PMI-RMP exam. PMI does not publish an official question count, but from its 230-minute exam (~90–155 total, ~12–20 in this domain), expect 6–10 from this objective — we provide 28 practice questions to prepare you well beyond it. (estimate)
28questions here
6free pages
6concepts
13%of the exam
Questions 21–25
- 21
A project manager implemented a risk response to mitigate the risk of a key team member leaving by cross-training another team member. After the cross-training is complete, the project manager evaluates the residual risk and finds that the likelihood of the key team member leaving is still 30%, but the impact is now reduced. The acceptable threshold for this risk is 25%. What should the project manager do?
Select an answer first - 22
During project execution, a risk response owner reports that the planned mitigation action for a high-priority risk has been completed. What is the most appropriate next step for the project manager?
Select an answer first - 23
A project's risk response plan specifies that if the cost of a key raw material increases by more than 10%, the project manager must switch to a substitute material. The cost increases by 12%. The project manager switches to the substitute material. What should the project manager do to ensure the response is effective?
Select an answer first - 24
A project team implements a risk response that involves outsourcing a critical component to a new vendor. What should the project manager do to identify secondary risks?
Select an answer first - 25
A project manager implemented a risk response to mitigate the risk of a critical equipment failure by purchasing a backup machine. After implementation, the project manager discovers that the backup machine requires a specialized operator who is not currently available. The residual risk of equipment failure is now 15%, but the acceptable threshold is 10%. What should the project manager do?
Select an answer first