Task 2 Implement Risk Response PMI-RMP Practice Questions (Page 3)
Part of the Risk Response domain, which accounts for 13% of the PMI-RMP exam. PMI does not publish an official question count, but from its 230-minute exam (~90–155 total, ~12–20 in this domain), expect 6–10 from this objective — we provide 28 practice questions to prepare you well beyond it. (estimate)
28questions here
6free pages
6concepts
13%of the exam
Questions 11–15
- 11
After implementing a risk response, the project manager assesses that the remaining risk level is 0.3 on a scale of 0 to 1. The organization's acceptable risk threshold is 0.5. What does this indicate?
Select an answer first - 12
A contingency plan is being executed because a risk trigger occurred. The contingency plan also fails to fully address the risk impact. What should the project manager do?
Select an answer first - 13
A project manager implemented a risk response to mitigate the risk of a key team member being unavailable by hiring a contractor. After the contractor starts, the project manager discovers that the contractor's work quality is below the project's standards, creating a new risk of rework. What should the project manager do?
Select an answer first - 14
Which of the following best describes a secondary risk?
Select an answer first - 15
A contingency plan for a project risk includes a trigger condition: 'If the vendor's delivery is delayed by more than 10 days, activate the backup supplier.' The vendor's delivery is now 12 days late. What should the project manager do?
Select an answer first
Finished these 5 questions?
Review the revealed explanations, or continue through the curriculum.
Free Basic Practice is a study aid with revealable answers — not a scored exam. Examers.io is independent and not affiliated with or endorsed by PMI. “PMI-RMP” is a trademark of its owner, used for identification only.