Task 2 Implement Risk Response PMI-RMP Practice Questions (Page 2)

Part of the Risk Response domain, which accounts for 13% of the PMI-RMP exam. PMI does not publish an official question count, but from its 230-minute exam (~90–155 total, ~12–20 in this domain), expect 6–10 from this objective — we provide 28 practice questions to prepare you well beyond it. (estimate)

28questions here
6free pages
6concepts
13%of the exam

Questions 6–10

  1. 6application · medium

    A software project has a contingency plan to activate a backup data center if the primary data center's uptime falls below 99.5% for a rolling 30-day period. The monitoring dashboard shows the current uptime is 99.4%. The operations team activates the backup data center. After activation, the project manager reviews the metrics and finds that the backup data center is operating at 99.6% uptime. What should the project manager do NEXT?

    Select an answer first
  2. 7foundation · easy

    After implementing a risk response, the project manager wants to know if the response was effective. Which action best supports this goal?

    Select an answer first
  3. 8application · medium

    A construction firm's risk response plan specifies that when the price of structural steel exceeds $1,200 per ton for two consecutive weeks, the procurement manager must sign a 6-month fixed-price contract with an alternative supplier. The trigger condition has just been met. The procurement manager signs the contract, but the alternative supplier's quality certification is still pending. What should the project manager do FIRST?

    Select an answer first
  4. 9application · medium

    A project manager implemented a risk response to reduce the impact of a potential network outage by adding a redundant internet connection. After implementation, the project manager evaluates the residual risk and finds that the impact is now minimal, but the likelihood of a complete outage is still 20%. The project's acceptable threshold for this risk is 15%. What should the project manager do?

    Select an answer first
  5. 10application · medium

    A project manager implemented a risk response to reduce the impact of a potential regulatory change by hiring a compliance consultant. After three months, the project manager wants to know if the response is effective. Which action is MOST aligned with the practice of encouraging stakeholder feedback?

    Select an answer first
Finished these 5 questions?

Review the revealed explanations, or continue through the curriculum.