Part of the Risk Identification domain, which accounts for 23% of the PMI-RMP exam. PMI does not publish an official question count, but from its 230-minute exam (~90–155 total, ~21–36 in this domain), expect 5–9 from this objective — we provide 27 practice questions to prepare you well beyond it. (estimate)
27questions here
6free pages
6concepts
23%of the exam
Questions 21–25
- 21
A project team identifies a potential cost saving from using a new technology. How should this be classified in the risk register?
Select an answer first - 22
A project team is developing a risk register for a software upgrade. They identify a risk that 'the new system may not integrate with legacy applications.' During a workshop, they discuss early warning signs. Which of the following is the most appropriate trigger to record for this risk?
Select an answer first - 23
During a risk review meeting, a team member proposes adding a risk that is already documented in the risk register with a different wording. What is the most appropriate action for the risk manager?
Select an answer first - 24
Why is assessing risk urgency important during risk attribute assessment?
Select an answer first - 25
A project manager is prioritizing risks for a software project. Risk A has a probability of 0.6 and an impact of $20,000. Risk B has a probability of 0.3 and an impact of $50,000. Risk C has a probability of 0.9 and an impact of $5,000. The project has limited resources for risk response. Which risk should be addressed first?
Select an answer first
Finished these 5 questions?
Review the revealed explanations, or continue through the curriculum.
Free Basic Practice is a study aid with revealable answers — not a scored exam. Examers.io is independent and not affiliated with or endorsed by PMI. “PMI-RMP” is a trademark of its owner, used for identification only.