Part of the Risk Identification domain, which accounts for 23% of the PMI-RMP exam. PMI does not publish an official question count, but from its 230-minute exam (~90–155 total, ~21–36 in this domain), expect 5–9 from this objective — we provide 27 practice questions to prepare you well beyond it. (estimate)
27questions here
6free pages
6concepts
23%of the exam
Questions 11–15
- 11
A project manager is updating the risk register for an IT infrastructure project. One risk is 'a critical team member may leave the project.' The project manager assigns the risk owner as the team member themselves. What is the primary issue with this assignment?
Select an answer first - 12
A project team is identifying risks for a new product launch. They identify that 'the product may receive positive media coverage, leading to increased sales.' They also identify that 'the product may receive negative media coverage, leading to decreased sales.' How should these be recorded in the risk register?
Select an answer first - 13
Which of the following best describes the purpose of risk validity analysis?
Select an answer first - 14
A project team is developing a risk register for a new product launch. They identify a risk that 'a key supplier may go out of business.' The supplier is external to the organization. Which of the following is the most appropriate risk owner for this risk?
Select an answer first - 15
A project manager is assigning owners for risks in a risk register. One risk is 'a regulatory change may affect the project's compliance requirements.' The project manager is considering several candidates. Which candidate is the most appropriate risk owner?
Select an answer first