Part of the Risk Identification domain, which accounts for 23% of the PMI-RMP exam. PMI does not publish an official question count, but from its 230-minute exam (~90–155 total, ~21–36 in this domain), expect 5–9 from this objective — we provide 27 practice questions to prepare you well beyond it. (estimate)

27questions here
6free pages
6concepts
23%of the exam

Questions 1–5

  1. 1expert · hard

    A project manager is developing a risk register for a global project. One risk is 'a change in foreign exchange rates may affect the project's procurement costs.' The project has suppliers in multiple countries. The project manager must assign a risk owner. Which of the following is the most appropriate owner?

    Select an answer first
  2. 2application · medium

    A project manager is assessing risks for a construction project. One risk is 'potential delays due to adverse weather.' The team has historical data showing a 30% chance of significant rain during the construction period. The impact is estimated at $50,000 in additional costs. Another risk is 'potential cost overrun due to material price increases,' with a 10% probability and $200,000 impact. Which risk should be prioritized higher in the risk register?

    Select an answer first
  3. 3foundation · easy

    What is the primary responsibility of a risk owner?

    Select an answer first
  4. 4application · medium

    A project manager is updating the risk register after a stakeholder workshop. One identified risk is 'potential delays due to vendor performance.' The vendor has a history of on-time delivery, and the contract includes penalties for late delivery. The project manager also notes that a similar risk already exists in the register for 'supplier capacity issues.' What should the project manager do with the new risk entry?

    Select an answer first
  5. 5foundation · easy

    A project manager notices that a key supplier's delivery delays are increasing. This pattern is an early warning sign that a risk may occur. What is this early warning sign called?

    Select an answer first