Part of the Risk Identification domain, which accounts for 23% of the PMI-RMP exam. PMI does not publish an official question count, but from its 230-minute exam (~90–155 total, ~21–36 in this domain), expect 5–9 from this objective — we provide 27 practice questions to prepare you well beyond it. (estimate)
27questions here
6free pages
6concepts
23%of the exam
Questions 6–10
- 6
When assessing a risk's attributes, which of the following is typically evaluated?
Select an answer first - 7
What is the purpose of classifying risks as threats or opportunities?
Select an answer first - 8
A project manager is developing a risk register for a manufacturing project. One risk is 'a key machine may break down due to lack of maintenance.' The maintenance team is internal to the organization. Which of the following is the most appropriate risk owner?
Select an answer first - 9
During a risk identification workshop, a stakeholder suggests that 'the new marketing campaign could go viral and increase sales by 20%.' The project manager is updating the risk register. How should this item be classified?
Select an answer first - 10
A risk is identified as arising from a change in government regulations. How should this risk be classified in terms of origin?
Select an answer first