Questions 21–24
- 21
A government agency implemented a new case management system. The acceptance criteria included the ability to handle 500 concurrent users and a response time of under 3 seconds. During user acceptance testing, the system met these criteria, but the implementation was rushed, and some training was skipped. The agency is now considering final sign-off. What should the business analyst do?
Select an answer first - 22
A financial services firm has completed user acceptance testing for a new customer onboarding application. All acceptance criteria have been met, and the test results have been documented. The business sponsor is ready to sign off, but the head of compliance has not yet reviewed the final test report. What should the business analyst do before recommending final sign-off?
Select an answer first - 23
A financial institution implemented a new anti-money laundering (AML) system. The implementation plan required a full data migration and a two-week parallel run. Due to a regulatory deadline, the parallel run was shortened to three days, and the system went live. The system is now detecting suspicious transactions, but the business analyst is reviewing the implementation and finds that the shortened parallel run may have missed some data validation issues. What should the business analyst do?
Select an answer first - 24
A manufacturing company deployed a predictive maintenance solution. The performance criteria defined during planning included a 20% reduction in unplanned downtime and a 15% reduction in maintenance costs. After a year, the solution has achieved a 25% reduction in downtime but only a 5% reduction in costs. The plant manager is pleased with the downtime reduction but concerned about the cost savings. What should the business analyst do?
Select an answer first
Finished these 4 questions?
Review the revealed explanations, or continue through the curriculum.
No more pagesBack to PMI-PBA
Free Basic Practice is a study aid with revealable answers — not a scored exam. Examers.io is independent and not affiliated with or endorsed by PMI. “PMI-PBA” is a trademark of its owner, used for identification only.