Task 3 Visualize Work PMI-ACP Practice Questions (Page 6)

Part of the Domain 3 Product domain, which accounts for 19% of the PMI-ACP exam. PMI does not publish an official question count, but from its 180-minute exam (~70–120 total, ~13–23 in this domain), expect 3–6 from this objective — we provide 32 practice questions to prepare you well beyond it. (estimate)

32questions here
7free pages
6concepts
19%of the exam

Questions 26–30

  1. 26foundation · easy

    Which action best ensures that a Kanban board remains accurate and timely?

    Select an answer first
  2. 27foundation · easy

    How does visualizing work primarily improve stakeholder communication?

    Select an answer first
  3. 28expert · hard

    A team uses a Kanban board and a burndown chart, but the burndown chart often shows a different story than the board. The team suspects the burndown chart is pulling data from a different source. What is the best way to resolve this discrepancy?

    Select an answer first
  4. 29expert · hard

    A co-located team uses a physical Kanban board, but the product owner, who works remotely, needs to see progress in real time. The team values the tactile nature of the physical board and does not want to abandon it. Which approach best satisfies both needs?

    Select an answer first
  5. 30application · medium

    A team's cumulative flow diagram (CFD) shows a widening band in the 'In Progress' column, but the team believes the data is inaccurate because members forget to move cards. What is the most reliable way to correct this?

    Select an answer first