Stakeholder Relationship and Risk Management PGMP Practice Questions (Page 3)

Part of the Stakeholder Engagement domain, which accounts for 16% of the PGMP exam. PMI does not publish an official question count, but from its 240-minute exam (~95–160 total, ~15–26 in this domain), expect 5–9 from this objective — we provide 28 practice questions to prepare you well beyond it. (estimate)

28questions here
6free pages
6concepts
16%of the exam

Questions 11–15

  1. 11foundation · easy

    After evaluating stakeholder-identified risks, what is the next step in integrating them into the program risk management plan?

    Select an answer first
  2. 12application · medium

    During a program risk review, a stakeholder from the finance department raises a concern about potential cost overruns due to currency fluctuations. The program manager has not previously considered this risk. What should the program manager do first?

    Select an answer first
  3. 13expert · hard

    A program manager is facilitating a risk identification workshop. A powerful sponsor repeatedly raises the same operational risk, which the program manager believes is already well-managed. The sponsor's insistence is consuming workshop time and may be masking other risks. The program manager must balance the sponsor's input with the need to identify a full range of risks. What should the program manager do?

    Select an answer first
  4. 14application · medium

    A program manager is leading a program that is experiencing delays. A key stakeholder is frustrated and has threatened to withdraw support. The program manager believes the delays are temporary and the program will recover. What is the best way to maintain the stakeholder's support?

    Select an answer first
  5. 15expert · hard

    A program manager is communicating with two key stakeholders who have conflicting communication preferences. Stakeholder A prefers detailed, data-heavy reports, while Stakeholder B prefers concise, high-level summaries. The program manager has limited time to prepare communications. What is the most effective approach?

    Select an answer first
Finished these 5 questions?

Review the revealed explanations, or continue through the curriculum.