Part of the Business Analysis Frameworks domain, which accounts for 27% of the CAPM exam. PMI does not publish an official question count, but from its 180-minute exam (~70–120 total, ~19–32 in this domain), expect 3–5 from this objective — we provide 22 practice questions to prepare you well beyond it. (estimate)

22questions here
5free pages
4concepts
27%of the exam

Questions 21–22

  1. 21application · easy

    A government agency is implementing a new public-facing benefits portal. The project team includes agency employees, a contractor who will build the portal, and a regulatory body that will audit the system. The public will use the portal to apply for benefits. Which of the following is an external stakeholder?

    Select an answer first
  2. 22application · easy

    A business analyst is working on a project for a hospital to implement a new patient records system. The stakeholders include the hospital's IT department, the medical staff, a software vendor, and a government health regulator. Which of the following is an internal stakeholder?

    Select an answer first
Finished these 2 questions?

Review the revealed explanations, or continue through the curriculum.

No more pagesBack to CAPM

Free Basic Practice is a study aid with revealable answers — not a scored exam. Examers.io is independent and not affiliated with or endorsed by PMI. “CAPM” is a trademark of its owner, used for identification only.