Which of the following is a common factor that can cause a team's velocity to vary from sprint to sprint?
Select an answer first - 27
A team's velocity dropped from 30 to 20 points in the last sprint. The team composition was the same, but the product owner added a large amount of unplanned work mid-sprint. What is the most likely cause of the drop?
Select an answer first