Track Team Velocity GITLAB-CERTIFIED-AGILE-PROJECT-MANAGEMENT-ASSOCIATE Practice Questions (Page 1)
Part of the Team Velocity and Tracking domain, which makes up ~26% of our current practice bank.
27questions here
6free pages
7concepts
Questions 1–5
- 1
A team's velocity increased from 20 to 30 story points after they switched to smaller story sizes. A manager wants to celebrate the team's increased productivity. How should the team respond?
Select an answer first - 2
A team completed three user stories in a sprint: Story A (8 points), Story B (5 points), and Story C (3 points). They also completed a 2-point bug fix that was not originally planned. What is the team's velocity for this sprint?
Select an answer first - 3
Which of the following statements correctly distinguishes velocity from productivity?
Select an answer first - 4
Why is velocity considered a planning metric rather than a productivity metric?
Select an answer first - 5
A velocity chart shows a sudden drop from 30 to 15 points in the latest sprint. The team reports that they completed all planned stories, but the product owner changed the Definition of Done mid-sprint to require additional testing. What is the most likely cause of the drop?
Select an answer first