Report on Delivery Progress GITLAB-CERTIFIED-AGILE-PROJECT-MANAGEMENT-ASSOCIATE Practice Questions (Page 1)
Part of the Team Velocity and Tracking domain, which makes up ~26% of our current practice bank.
25questions here
5free pages
5concepts
Questions 1–5
- 1
What does a velocity chart primarily show?
Select an answer first - 2
How can a team use the average velocity from recent sprints?
Select an answer first - 3
A team has completed three sprints. Sprint 1 delivered 20 story points, Sprint 2 delivered 25, and Sprint 3 delivered 30. The product owner asks for a forecast of how many story points the team is likely to deliver in the next sprint. Based on the velocity chart, what is the most appropriate estimate to communicate?
Select an answer first - 4
A project manager needs to communicate to executives whether the team is delivering at a sustainable pace and how much work is likely to be completed in the next release. Which combination of charts would best support this report?
Select an answer first - 5
When reporting delivery progress to stakeholders, which metric is most useful to show the team's overall delivery capacity?
Select an answer first