Report on Delivery Progress GITLAB-CERTIFIED-AGILE-PROJECT-MANAGEMENT-ASSOCIATE Practice Questions (Page 4)

Part of the Team Velocity and Tracking domain, which makes up ~26% of our current practice bank.

25questions here
5free pages
5concepts

Questions 16–20

  1. 16application · medium

    A team's velocity chart shows a significant drop in the last sprint, from an average of 30 story points to 18. The team reports that two members were on vacation and a critical dependency was delayed. How should the scrum master report this to stakeholders?

    Select an answer first
  2. 17application · medium

    A team wants to report to stakeholders on how much work they complete per sprint and whether they are improving over time. Which metric and chart combination is most appropriate?

    Select an answer first
  3. 18application · medium

    A sprint burn-down chart shows the remaining work line dropping below the ideal line early in the sprint. What does this indicate?

    Select an answer first
  4. 19foundation · easy

    What does a cumulative flow diagram (CFD) help a team identify?

    Select an answer first
  5. 20application · medium

    A cumulative flow diagram shows the 'In Review' band growing steadily while the 'Done' band stays flat. The team has a WIP limit of 3 for review. What is the most likely issue?

    Select an answer first