Use Milestones and Burndown Charts GITLAB-CERTIFIED-AGILE-PROJECT-MANAGEMENT-ASSOCIATE Practice Questions (Page 1)
Part of the Team Velocity and Tracking domain, which makes up ~26% of our current practice bank.
22questions here
5free pages
5concepts
Questions 1–5
- 1
Where can you view the progress percentage of a milestone in GitLab?
Select an answer first - 2
A project manager wants to use a burndown chart to monitor the progress of a two-week sprint. The team has a mix of issues and merge requests that need to be completed. What must be done to ensure the burndown chart accurately reflects the sprint's work?
Select an answer first - 3
What does the line on a burndown chart represent?
Select an answer first - 4
If the burndown chart line suddenly moves upward during a sprint, what is the most likely cause?
Select an answer first - 5
Which GitLab items can be assigned to a milestone?
Select an answer first