Use Milestones and Burndown Charts GITLAB-CERTIFIED-AGILE-PROJECT-MANAGEMENT-ASSOCIATE Practice Questions (Page 4)

Part of the Team Velocity and Tracking domain, which makes up ~26% of our current practice bank.

22questions here
5free pages
5concepts

Questions 16–20

  1. 16foundation · easy

    In GitLab, how do you associate an issue with a milestone?

    Select an answer first
  2. 17application · medium

    A project manager is reviewing the milestone progress page and sees that the percentage of completed issues is 60%, but the burndown chart shows a flat line for the last three days. What does this combination most likely indicate?

    Select an answer first
  3. 18foundation · easy

    Which of the following is a required field when creating a milestone in GitLab?

    Select an answer first
  4. 19application · medium

    A project manager is using a burndown chart to monitor a sprint. The chart shows that the remaining work line is consistently below the ideal line. What does this indicate about the team's velocity?

    Select an answer first
  5. 20expert · hard

    A team is using a milestone to track a sprint. The burndown chart shows that the remaining work line is consistently above the ideal line, but the team reports they are working at full capacity. What is the most likely explanation?

    Select an answer first