Use Milestones and Burndown Charts GITLAB-CERTIFIED-AGILE-PROJECT-MANAGEMENT-ASSOCIATE Practice Questions (Page 3)

Part of the Team Velocity and Tracking domain, which makes up ~26% of our current practice bank.

22questions here
5free pages
5concepts

Questions 11–15

  1. 11foundation · easy

    When creating a new milestone in GitLab, which three fields are available to define the milestone?

    Select an answer first
  2. 12foundation · easy

    If a burndown chart shows a line that is consistently above the ideal trend line, what does this indicate?

    Select an answer first
  3. 13expert · hard

    A team is using a burndown chart for a sprint. The chart shows a flat line for the first three days, then a steep downward slope for the next two days. What is the most likely explanation?

    Select an answer first
  4. 14foundation · easy

    What is a common use of a burndown chart during a sprint?

    Select an answer first
  5. 15expert · hard

    A project manager is using a burndown chart to monitor a sprint. The chart shows a sudden upward spike in remaining work on day 5. The team confirms they did not add any new issues. What is the most likely cause of the spike?

    Select an answer first