Use Milestones and Burndown Charts GITLAB-CERTIFIED-AGILE-PROJECT-MANAGEMENT-ASSOCIATE Practice Questions (Page 5)

Part of the Team Velocity and Tracking domain, which makes up ~26% of our current practice bank.

22questions here
5free pages
5concepts

Questions 21–22

  1. 21expert · hard

    A project manager is creating a milestone for a sprint that starts in two weeks. The team wants to track progress using a burndown chart. What should the project manager do to ensure the burndown chart is available from the first day of the sprint?

    Select an answer first
  2. 22application · medium

    A team is using a burndown chart for a sprint. The chart shows a steep downward slope in the first half, then a flat line for the second half. What is the most likely interpretation?

    Select an answer first
Finished these 2 questions?

Review the revealed explanations, or continue through the curriculum.