Questions 11–15
- 11
Which chart is best for showing both the total scope and the completed work over time?
Select an answer first - 12
A team has a stable velocity of 25 story points per sprint, but the last sprint delivered only 15 because of an unexpected outage. The product owner asks for a forecast for the next sprint. What is the most appropriate forecast to communicate?
Select an answer first - 13
A team's cumulative flow diagram shows the 'In Progress' band widening, but the team has a WIP limit of 4 and is consistently at that limit. The 'Done' band is flat. What is the most effective action to improve flow?
Select an answer first - 14
A team's cumulative flow diagram shows the 'To Do' band shrinking while the 'In Progress' band is growing, but the 'Done' band is unchanged. What should the team investigate first?
Select an answer first - 15
A team's burn-up chart shows the total scope line rising sharply mid-sprint, and the completed work line is also rising but at a slower rate. The product owner wants to know if the team will still meet the sprint goal. What is the most important factor to communicate?
Select an answer first