  1. 16application · medium

    A team's velocity for the last four sprints was 18, 22, 20, and 24 story points. The team will have two members on training for two days during the next sprint. What is the best estimate for the team's capacity?

    Select an answer first
  2. 17application · easy

    A team's velocity over the last five sprints was 24, 28, 26, 25, and 27 story points. The product owner wants to know how many story points the team can likely commit to in the next sprint. What should the team use as the basis for this forecast?

    Select an answer first
  3. 18application · medium

    A team's velocity chart shows values of 30, 32, 31, 33, and 32 over five sprints. In the next sprint, the team will have a new junior developer joining. What is the best way to use the velocity chart for planning?

    Select an answer first
  4. 19application · easy

    A team has been tracking velocity for six sprints. The values are 20, 22, 21, 23, 22, and 24. The team is planning the next sprint and wants to use the velocity chart to forecast. What is the most reliable forecast?

    Select an answer first
  5. 20foundation · easy

    What is the primary purpose of maintaining a velocity chart that spans several sprints?

    Select an answer first