Questions 11–15
- 11
A team completed 40 story points in a sprint, but 10 of those points were for stories that were not fully done according to the Definition of Done. What is the team's velocity for that sprint?
Select an answer first - 12
A team's velocity for the last four sprints was 30, 32, 31, and 29 story points. In the upcoming sprint, one developer will be on vacation for half the sprint. What is the most appropriate planning approach?
Select an answer first - 13
How should a team use historical velocity data when planning an upcoming sprint?
Select an answer first - 14
Why is it valuable to track velocity across multiple sprints?
Select an answer first - 15
Which of the following best describes the unit of measure for velocity in an Agile team?
Select an answer first