- 6
A team's velocity has been steadily decreasing over the last three sprints. The team composition and scope have remained constant. What is the most likely factor to investigate?
Select an answer first - 7
A team completes four user stories in a sprint with story point estimates of 3, 5, 8, and 2. What is the team's velocity for that sprint?
Select an answer first - 8
A team's velocity dropped significantly in the last sprint. Which of the following is a plausible reason for this variation?
Select an answer first - 9
A team has been tracking velocity for 10 sprints. The values are 20, 22, 21, 23, 22, 24, 21, 23, 22, and 24. The team is about to start a new project with a different domain and expects the work to be more complex. How should they plan the first sprint of the new project?
Select an answer first - 10
A team's velocity chart shows a steady increase from 20 to 30 points over six sprints. The team has had the same members and the same product owner. What is the most likely explanation for this trend?
Select an answer first
Finished these 5 questions?
Review the revealed explanations, or continue through the curriculum.
Free Basic Practice is a study aid with revealable answers — not a scored exam. Examers.io is independent and not affiliated with or endorsed by GitLab. “GITLAB-CERTIFIED-AGILE-PROJECT-MANAGEMENT-ASSOCIATE” is a trademark of its owner, used for identification only.