Examers.io
ExamsOrganizationsHow it worksPricingHelp & FAQ
CompTIA logo

CompTIAProject+

Domain 1Objective 4

Risk Management PK0-005 Practice Questions (Page 7)

Part of the Project management concepts domain, which accounts for 33% of the PK0-005 exam. CompTIA does not publish an official question count, but from its 90-minute exam (~35–60 total, ~12–20 in this domain), expect 1–2 from this objective — we provide 32 practice questions to prepare you well beyond it. (estimate)

32questions here
7free pages
7concepts
33%of the exam

Questions 31–32

  1. 31application · medium

    A software project has a risk that a third-party API may be discontinued, which would require significant rework. The project manager decides to build an abstraction layer to make it easier to switch to another API. Which risk response strategy is being used?

    Select an answer first
  2. 32foundation · easy

    What is the primary purpose of conducting regular risk reviews during project execution?

    Select an answer first
Finished these 2 questions?

Review the revealed explanations, or continue through the curriculum.

No more pagesBack to PK0-005

Free Basic Practice is a study aid with revealable answers — not a scored exam. Examers.io is independent and not affiliated with or endorsed by CompTIA. “PK0-005” is a trademark of its owner, used for identification only.