Risk Management PK0-005 Practice Questions (Page 3)
Part of the Project management concepts domain, which accounts for 33% of the PK0-005 exam. CompTIA does not publish an official question count, but from its 90-minute exam (~35–60 total, ~12–20 in this domain), expect 1–2 from this objective — we provide 32 practice questions to prepare you well beyond it. (estimate)
32questions here
7free pages
7concepts
33%of the exam
Questions 11–15
- 11
A project team decides to purchase insurance to cover potential financial losses from a specific risk. This is an example of which risk response strategy?
Select an answer first - 12
A project manager is prioritizing risks for a new product launch. The team has identified three risks: Risk A has a high probability and high impact, Risk B has a low probability and high impact, and Risk C has a high probability and low impact. Which risk should be addressed first?
Select an answer first - 13
A project team is conducting a risk identification workshop. A senior developer mentions that a new government regulation might affect the project's data handling requirements. What should the project manager do with this information?
Select an answer first - 14
A project manager is facilitating a risk identification session. To encourage participation, which technique should be used to generate a broad list of potential risks from the team?
Select an answer first - 15
A project manager is evaluating risks to decide which ones need immediate attention. The team rates each risk's probability and impact on a scale of 1 to 5. This approach is an example of which risk management process?
Select an answer first