Part of the Project management concepts domain, which accounts for 33% of the PK0-005 exam. CompTIA does not publish an official question count, but from its 90-minute exam (~35–60 total, ~12–20 in this domain), expect 1–2 from this objective — we provide 32 practice questions to prepare you well beyond it. (estimate)
32questions here
7free pages
7concepts
33%of the exam
Questions 16–20
- 16
A project manager is using a Monte Carlo simulation to analyze the impact of schedule risks on the project completion date. What is the primary benefit of this quantitative technique?
Select an answer first - 17
A project manager is planning responses for a high-impact risk that could delay the project by three weeks. The team has proposed three options: (1) hire a consultant to reduce the delay to one week at a cost of $20,000, (2) accept the risk and use the project buffer, or (3) transfer the risk by purchasing insurance that covers the cost of the delay. The project has a tight budget but a large schedule buffer. Which response should the project manager choose?
Select an answer first - 18
During the planning phase of a software development project, the project manager wants to systematically identify potential risks that could affect the project's success. Which activity is most directly associated with risk identification?
Select an answer first - 19
In qualitative risk analysis, what is the primary purpose of creating a probability and impact matrix?
Select an answer first - 20
What is the primary purpose of maintaining a risk register throughout the project?
Select an answer first