Risk Management PK0-005 Practice Questions (Page 5)
Part of the Project management concepts domain, which accounts for 33% of the PK0-005 exam. CompTIA does not publish an official question count, but from its 90-minute exam (~35–60 total, ~12–20 in this domain), expect 1–2 from this objective — we provide 32 practice questions to prepare you well beyond it. (estimate)
32questions here
7free pages
7concepts
33%of the exam
Questions 21–25
- 21
A project manager decides to change the project approach to completely eliminate a high-impact risk. This is an example of which risk response strategy?
Select an answer first - 22
A project manager is reviewing the risk register during a status meeting. A risk that was previously rated as high probability and high impact has not occurred, but the team has implemented a mitigation plan. What should the project manager do?
Select an answer first - 23
A project manager is reviewing the risk register and finds that several risks have not been updated since the project started. The project is halfway through execution. What is the most important reason to update the risk register regularly?
Select an answer first - 24
A project manager is assigning risk owners for a list of identified risks. One risk involves a potential security breach in the new software. The project manager assigns the risk to the lead developer. What is the primary responsibility of the risk owner?
Select an answer first - 25
Which document is used to record identified risks, their analysis, and planned responses?
Select an answer first