Part of the Business Environment domain, which accounts for 26% of the PMP exam. PMI does not publish an official question count, but from its 230-minute exam (~90–155 total, ~23–40 in this domain), expect 3–5 from this objective — we provide 31 practice questions to prepare you well beyond it. (estimate)
31questions here
7free pages
7concepts
26%of the exam
Questions 6–10
- 6
What is the key indicator that a risk has transitioned into an issue?
Select an answer first - 7
The project manager has identified three impediments: a minor documentation delay, a critical security vulnerability, and a team member's absence. Which impediment should be prioritized for immediate attention?
Select an answer first - 8
A project team identified a risk that a key supplier might go out of business. The supplier has now announced bankruptcy, and the project cannot proceed without their components. How should the project manager handle this situation?
Select an answer first - 9
Why is it important to continually reassess impediments during a project?
Select an answer first - 10
A project team member reports that a critical software component is delayed. The project manager needs to understand how this delay will affect the project's deliverables and objectives. Which action best evaluates the impediment's impact?
Select an answer first