Task 4 Remove Impediments and Manage Issues PMP Practice Questions (Page 1)
Part of the Business Environment domain, which accounts for 26% of the PMP exam. PMI does not publish an official question count, but from its 230-minute exam (~90–155 total, ~23–40 in this domain), expect 3–5 from this objective — we provide 31 practice questions to prepare you well beyond it. (estimate)
31questions here
7free pages
7concepts
26%of the exam
Questions 1–5
- 1
A project team is blocked by a regulatory approval that is taking longer than expected. The project manager has assessed the impact and determined this is the top impediment. What should the project manager do to gain support for resolving it?
Select an answer first - 2
Which of the following is an example of an intervention strategy to remove an impediment?
Select an answer first - 3
A project manager resolved a critical issue by implementing a contingency plan. The project manager is now reviewing the situation and notices that the issue has not fully resolved as expected. What should the project manager do?
Select an answer first - 4
A project manager is reviewing the project schedule and notices that a critical path activity is delayed because a team member is out sick. The project manager has identified this as an impediment. What should the project manager do FIRST?
Select an answer first - 5
A project manager implemented a workaround for a critical impediment. The workaround is working, but the project manager is concerned it may not be sustainable. What should the project manager do?
Select an answer first
Finished these 5 questions?
Review the revealed explanations, or continue through the curriculum.