Part of the Business Environment domain, which accounts for 26% of the PMP exam. PMI does not publish an official question count, but from its 230-minute exam (~90–155 total, ~23–40 in this domain), expect 3–5 from this objective — we provide 27 practice questions to prepare you well beyond it. (estimate)
27questions here
6free pages
4concepts
26%of the exam
Questions 1–5
- 1
An approved change requires the project team to use a new software tool for testing. What should the project manager do to ensure the change is effectively implemented?
Select an answer first - 2
A project manager is managing a project with multiple stakeholders. A change request is deferred by the CCB because more information is needed. The requester is upset and demands an immediate decision. What should the project manager do?
Select an answer first - 3
After the change control board (CCB) makes a decision on a change request, what must the project manager do?
Select an answer first - 4
After a change request is approved, what should the project manager do to integrate the change into the project?
Select an answer first - 5
A project manager has just received approval for a change that adds a new deliverable to the project scope. Which document should the project manager update to reflect this change?
Select an answer first