Part of the Business Environment domain, which accounts for 26% of the PMP exam. PMI does not publish an official question count, but from its 230-minute exam (~90–155 total, ~23–40 in this domain), expect 3–5 from this objective — we provide 27 practice questions to prepare you well beyond it. (estimate)
27questions here
6free pages
4concepts
26%of the exam
Questions 11–15
- 11
A project manager is managing a project where a change request has been approved, but the requester is not satisfied with the implementation timeline. The requester threatens to escalate to senior management. What should the project manager do?
Select an answer first - 12
A change request to replace a third-party vendor has been approved by the change control board. What should the project manager do first to integrate this change into the project?
Select an answer first - 13
A project manager has implemented a series of approved changes. During a status review, the project manager notices that the project documentation does not reflect all the changes. What should the project manager do?
Select an answer first - 14
After an approved change is implemented, which document should be updated to record the change and its details?
Select an answer first - 15
A project manager is managing a large infrastructure project. A change request is submitted to replace a critical component. The change control board (CCB) is divided: some members want to approve it to avoid future failures, while others want to reject it due to cost. The project manager must facilitate the decision. What should the project manager do to ensure an informed decision?
Select an answer first