Task 7 Plan and Optimize Quality of Products/deliverables PMP Practice Questions (Page 4)

Part of the Process domain, which accounts for 41% of the PMP exam. PMI does not publish an official question count, but from its 230-minute exam (~90–155 total, ~37–64 in this domain), expect 4–6 from this objective — we provide 33 practice questions to prepare you well beyond it. (estimate)

33questions here
7free pages
8concepts
41%of the exam

Questions 16–20

  1. 16foundation · easy

    A project manager is documenting the quality requirements for a construction project. Which document should contain the specific quality standards and acceptance criteria for the project's deliverables?

    Select an answer first
  2. 17application · medium

    A medical device manufacturer is planning a new product launch. The project manager is defining quality requirements for the device's software component. The regulatory affairs team has confirmed that the device must comply with FDA cybersecurity guidelines, and the marketing team has requested a feature that automatically updates the device's firmware over the internet. The project sponsor is concerned about the cost of implementing the update feature. What should the project manager do first?

    Select an answer first
  3. 18application · medium

    A project manager is working on a project to develop a new mobile app for a healthcare provider. The app will handle patient data, and the project must comply with HIPAA regulations. The product owner has requested a feature that allows patients to share their health data with third-party apps. The project manager needs to define quality requirements. What should the project manager do?

    Select an answer first
  4. 19foundation · easy

    Which cost category is an example of a prevention cost in the cost of quality?

    Select an answer first
  5. 20application · medium

    A manufacturing project manager is planning quality for a new product line. The team has identified that the cost of rework is high, and the project sponsor wants to reduce overall quality costs. The project manager is considering investing in better training for the production staff. What should the project manager do?

    Select an answer first